Objectives:
During FY 2014-15, Assam State Rural Livelihoods Mission (ASRLM) partnered with Kerala State Poverty Eradication Mission, Kudumbashree - NRO for implementing PRI CBO (Panchayati Raj Institutions - Community Based Organisations) Convergence Pilot Project in Assam in 36 pilot GPs of two blocks of Laharighat and Bajiagaon in Morigaon and Nagaon districts respectively.The main objective of the partnership between ASRLM and Kudumbashree NRO was to create a model for supporting both PRI and CBO networks for effective convergence leading to sustainable and better implementation of NRLM. In the long run, it should result in the creation of a robust institutional structure of the poor that is closely linked to local governance and development.
Assam was a forerunner amongst other states doing the Convergence pilot project. Now, ASRLM is scaling up the pilot project to 4 new blocks i.e. Barhampur (Nagaon), Laokhowa(Nagaon), Dhekiajuli(Sonitpur) and Borsala(Sonitpur) at first phase from FY 2017-18 onwards. The internal pool (Internal Mentors) developed during the piloting are helping in scaling up the PRI-CBO Convergence project. Kudumbashree- NRO, Kerala has been handholding the Internal Mentors in the scaling up programme. The number of panchayats in the new blocks total to 51. Govt. of Assam is also contemplating to replicate this PRI-CBO Convergence to all blocks of Assam in near future. In its first phase of Expansion,19 blocks have been selected for the project.
Rational for the selection of Blocks:
Only 19 blocks can be taken due to the lack of internal cadre (Internal mentors) for the financial year 2018-19
These blocks will be strengthened as Resource blocks for PRI-CBO convergence project because of the following results emerged out of the project:
Progress during FY 17-18 and FY 18-19: Sensitization Campaign for Stakeholders:
MAJOR ACTIVITY |
STATUS OF THE ACTIVITY |
|
1 |
Orientation to DMMU and BMMU staff |
|
2 |
Orientation to line department officials |
|
3 |
Orientation to JSs |
|
4 |
PRI Orientation |
Initial orientation (cluster level) to the PRI members
|
Developing Local Resource Group Cadre:
MAJOR ACTIVITY |
STATUS OF THE ACTIVITY |
|
1 |
LRG identification and Selection |
Selected LRGs for all the panchayats
|
2 |
LRG training |
Initial Training for the LRGs selected:
|
3 |
Other Trainings for LRGs |
|
4 |
Review meetings |
Monthly monitoring by Internal mentors, Quarterly monitoring by mission staff and external mentors |
Identification and developing of Internal Mentors:
MAJOR ACTIVITY |
STATUS OF THE ACTIVITY |
|
1 |
Internal mentor training - Phase I |
|
2 |
Internal mentor selection -Phase II |
|
3 |
Other trainings |
|
4 |
Review Meetings |
Monthly review meetings with SPC/FC , Mentors and Mission staff |
Gram Sabha - Then and Now:
Innovative Activities: